Schedule

1st QUARTER

Structure

  • Erecting ETFE Sections
  • Stretch ETFE Fabric
  • Installing Moat Lids
  • Setting Exterior Metal Panels
  • Working on Structure of Oculus

Interiors

  • Continue to work on MEP Rough-ins
  • Continue to work on All Finishes in the building
  • Installing Seats
  • Installing Sports Lights
  • Install Video Board Panels on Oculus
  • Installing Speakers
  • Installing Ribbon Board Video Panels

Site Work

  • Continue to develop Parking Lots
  • Continue to develop Streets
  • Continue to Install Landscaping
  • Continue to work on the retaining wall
  • Continue to work in American Airlines Plaza
  • Continue to Develop Lake Park

Performance Venue

  • Continue to set precast stadia
  • Continue to work on the new north Façade
  • Develop the on grade seating bowl
  • Continue to work on MEP Rough-ins
  • Continue to work on the Enclosure

 Superstructure

  • Blade Columns – Complete
  • Stadium Canyon Work – Ongoing
  • Bowl Steel and Precast – Complete
  • MEP/Rough-ins and Interior Finishes – Ongoing

2nd QUARTER

Structure

  • Finish Erecting ETFE Sections
  • Finish Stretching ETFE Fabric
  • Raise Oculus to the Final Position

Interiors

  • Continue to work on All Finishes in the building
  • Installing Sports Lights
  • Testing Video Board on Oculus
  • Testing Speakers
  • Finalize Ribbon Board Video Panels

Site Work

  • Continue to develop Parking Lots
  • Continue to develop Streets
  • Continue to Install Landscaping
  • Continue to work in American Airlines Plaza
  • Continue to Develop Lake Park

Performance Venue

  • Continue to work on the new north Façade
  • Continue to work on MEP Rough-ins
  • Continue to work on the Enclosure

 Superstructure

  • Stadium Canyon Work – Ongoing
  • Bowl Steel and Precast – Complete
  • MEP/Rough-ins and Interior Finishes