Schedule

1st QUARTER

Substructure

  • Roof Skeleton Shell will complete
  • Roof Cabling – Start
  • Excavation of Lake – Start
  • Interior Build Out-Ongoing
  • Dry-In Interiors -Start
  • Gas Service to Stadium -Start
  • Retaining Wall -Start
  • Flat work to start from Stadium to Dripline work -Start
  • Champions Plaza and VIP – End Field-Start

Superstructure

  • Blade Columns – Complete
  • Stadium Canyon work – Ongoing
  • Bowl Steel and Precast – complete
  • MEP /Rough-In and Interior Finishes– Ongoing

Site Work

  • Parking Lot Grading-Start
  • Temp Ramp Backfill
  • Performance Venue – Structural -Start
  • Underground Site Utilities-Ongoing

 

2nd QUARTER

Substructure

  • Roof Cabling – Ongoing
  • Lake – On going
  • Retaining Wall – Ongoing
  • Dry-In Interiors
  • Gas Service to Stadium-Ongoing
  • Retaining Wall – Complete
  • Flatwork to start from Stadium to Dripline work – Ongoing
  • Champions Plaza and VIP – End Field Ongoing

Superstructure

  • Stadium Canyon work – Ongoing
  • Bowl Steel and Precast – complete
  • MEP /Rough-In and Interior Finishes

Site Work

  • Parking Lot Grading – Ongoing
  • Temp Ramp Backfill – Complete
  • Performance Venue – Structural – Ongoing